πŸ“Š Management Science
Q. For decision making under uncertainty, identify the decision rule that is appropriate for the optimist.
  • (A) laplace
  • (B) maximax
  • (C) minimax regret
  • (D) maxmin
πŸ’¬ Discuss
βœ… Correct Answer: (B) maximax
πŸ“Š Management Science
Q. In a decision theory problem under complete uncertainty, which one of the following approaches will not be possible?
  • (A) expected monetary value
  • (B) maxmin
  • (C) minimax
  • (D) hurwicz
πŸ’¬ Discuss
βœ… Correct Answer: (A) expected monetary value
πŸ“Š Management Science
Q. If a decision theory problem has 3 decision alternatives and 4 states of nature, the number of payoffs in that problem will be
  • (A) 3
  • (B) 4
  • (C) 12
  • (D) 64
πŸ’¬ Discuss
βœ… Correct Answer: (C) 12
πŸ“Š Management Science
Q. Which of the following is not a part of decision tree problem specification?
  • (A) a list of alternatives
  • (B) a list of possible state of nature
  • (C) evpi
  • (D) pay off associated with alternative/ state of nature combination.
πŸ’¬ Discuss
βœ… Correct Answer: (C) evpi
πŸ“Š Management Science
Q. ………is the shortest possible time in which an activity can be delayed without delaying the project.
  • (A) pessimistic time estimate
  • (B) optimistic time estimate
  • (C) most likely time estimate
  • (D) none of these
πŸ’¬ Discuss
βœ… Correct Answer: (B) optimistic time estimate
πŸ“Š Management Science
Q. ………… is the duration by which an activity can be delayed without delaying the project.
  • (A) total float
  • (B) slack
  • (C) earliest event time
  • (D) none of these
πŸ’¬ Discuss
βœ… Correct Answer: (A) total float
πŸ“Š Management Science
Q. …………..is an activity oriented diagram.
  • (A) cpm
  • (B) pert
  • (C) histogram
  • (D) none of the above
πŸ’¬ Discuss
βœ… Correct Answer: (A) cpm
πŸ“Š Management Science
Q. …….is the disconnection of an activity before the completion of activities in a project network diagram.
  • (A) dangling
  • (B) looping
  • (C) dummy
  • (D) none of the above
πŸ’¬ Discuss
βœ… Correct Answer: (C) dummy
πŸ“Š Management Science
Q. The event is commonly represented by …… in network diagram
  • (A) nodes
  • (B) arrow
  • (C) triangle
  • (D) none of these
πŸ’¬ Discuss
βœ… Correct Answer: (A) nodes
πŸ“Š Management Science
Q. An activity which must be completed before one or more other activities start is known as …………activity.
  • (A) dummy
  • (B) predecessor
  • (C) successor
  • (D) none of these
πŸ’¬ Discuss
βœ… Correct Answer: (B) predecessor