R Rakesh Kumar π Hard Worker β 28.44K Points π Management Science Q. For decision making under uncertainty, identify the decision rule that is appropriate for the optimist. (A) laplace (B) maximax (C) minimax regret (D) maxmin ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (B) maximax
V Vikash Gupta π Tutor III β 33.56K Points π Management Science Q. In a decision theory problem under complete uncertainty, which one of the following approaches will not be possible? (A) expected monetary value (B) maxmin (C) minimax (D) hurwicz ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (A) expected monetary value
G Gopal Sharma π Tutor III β 38.32K Points π Management Science Q. If a decision theory problem has 3 decision alternatives and 4 states of nature, the number of payoffs in that problem will be (A) 3 (B) 4 (C) 12 (D) 64 ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (C) 12
R Ram Sharma π Coach β 193.88K Points π Management Science Q. Which of the following is not a part of decision tree problem specification? (A) a list of alternatives (B) a list of possible state of nature (C) evpi (D) pay off associated with alternative/ state of nature combination. ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (C) evpi
R Ranjeet π Tutor III β 34.60K Points π Management Science Q. ………is the shortest possible time in which an activity can be delayed without delaying the project. (A) pessimistic time estimate (B) optimistic time estimate (C) most likely time estimate (D) none of these ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (B) optimistic time estimate
V Vinay π Mover β 28.75K Points π Management Science Q. ………… is the duration by which an activity can be delayed without delaying the project. (A) total float (B) slack (C) earliest event time (D) none of these ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (A) total float
A Admin π Coach β 38.23K Points π Management Science Q. …………..is an activity oriented diagram. (A) cpm (B) pert (C) histogram (D) none of the above ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (A) cpm
R Ram Sharma π Coach β 193.88K Points π Management Science Q. …….is the disconnection of an activity before the completion of activities in a project network diagram. (A) dangling (B) looping (C) dummy (D) none of the above ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (C) dummy
S Shiva Ram π Master β 30.44K Points π Management Science Q. The event is commonly represented by …… in network diagram (A) nodes (B) arrow (C) triangle (D) none of these ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (A) nodes
A Admin π Coach β 38.23K Points π Management Science Q. An activity which must be completed before one or more other activities start is known as …………activity. (A) dummy (B) predecessor (C) successor (D) none of these ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (B) predecessor