πŸ“Š Production Management
Q. __________ involves identifying the manpower requirements, machine capacity, and materials required to meet the planned production targets.
  • (A) Routing
  • (B) Estimating
  • (C) Scheduling
  • (D) Dispatching
πŸ’¬ Discuss
βœ… Correct Answer: (B) Estimating
πŸ“Š Production Management
Q. The process of relocation of workers should result in
  • (A) Facilitating the operations
  • (B) Equalized production at different work stations
  • (C) Better utilization of equipment
  • (D) Verifying the proper jigs
πŸ’¬ Discuss
βœ… Correct Answer: (C) Better utilization of equipment
πŸ“Š Production Management
Q. Which of the following are quality control tools? 1. Pareto diagrams 2. Flow charts 3. Work measurement quantities 4. Cause and effect diagrams
  • (A) Options 1, 2 & 3
  • (B) Options 1, 2 &4
  • (C) Options 2, 3 & 4
  • (D) Options 1, 3 & 4
πŸ’¬ Discuss
βœ… Correct Answer: (B) Options 1, 2 &4
πŸ“Š Production Management
Q. Which of the following are pitfalls of subcontracting? 1. It lowers the morale of all workers 2. It wears out the workers and the overall productivity drops off 3. It risks opening the clients door to a competitor 4. It may be expensive
  • (A) Options 1 & 2
  • (B) Options 1 & 3
  • (C) Options 3 & 4
  • (D) Options 2 & 3
πŸ’¬ Discuss
βœ… Correct Answer: (C) Options 3 & 4
πŸ“Š Production Management
Q. Which of the following are inputs received during the design phase? 1. Functional specifications of the project 2. System design specifications 3. Preliminary project evaluation details 4. Project proposal
  • (A) Options 1 & 2
  • (B) Options 1 & 3
  • (C) Options 3 & 4
  • (D) Options 2 & 3
πŸ’¬ Discuss
βœ… Correct Answer: (C) Options 3 & 4
πŸ“Š Production Management
Q. _________ plan and manage the project on a day-to-day basis for this stage _________ define the coordination, control activities and identify the suitable personnel to carry them out.
  • (A) Project coordinators, stage teams
  • (B) Stage managers, project coordinators
  • (C) Stage teams, key stakeholders
  • (D) Stage managers, key stakeholders
πŸ’¬ Discuss
βœ… Correct Answer: (B) Stage managers, project coordinators
πŸ“Š Production Management
Q. Project process is classified into two main categories and
  • (A) Project management process, planning process
  • (B) Initiating process, product oriented process
  • (C) Product oriented process, project management process
  • (D) Planning processes, initiating process
πŸ’¬ Discuss
βœ… Correct Answer: (C) Product oriented process, project management process
πŸ“Š Production Management
Q. The outcomes of the logical model and physical model are called the_____________ and______________
  • (A) Control flow diagrams, business process diagrams
  • (B) Business process diagrams, data flow diagrams
  • (C) Entity relationship diagrams, business process diagrams
  • (D) Entity relationship diagrams, control flow diagrams
πŸ’¬ Discuss
βœ… Correct Answer: (C) Entity relationship diagrams, business process diagrams
πŸ“Š Production Management
Q. Histograms are used for which of the following?
1. To record huge volumes of data about a process.
2. To indicate the extent of each category of problems in descending order of magnitude of the problem
3. To reveal if the pattern of distribution has a single peak, or many peaks.
4. To locate the points at which a problem exists.
  • (A) Options 1 & 2
  • (B) Options 2 & 3
  • (C) Options 1 & 3
  • (D) Options 1 & 4
πŸ’¬ Discuss
βœ… Correct Answer: (D) Options 1 & 4
πŸ“Š Production Management
Q. Which of the following are the features of process layout?
1 Emphasis is on special orders or products having significant and frequent design changes.
2. Standardized product with little or no design changes.
3. Minimum requirement of in-process inspection.
4. Use of general purpose machines.
  • (A) Options 3 & 4
  • (B) Options 1 & 4
  • (C) Options 1 & 2
  • (D) Options 2 & 3
πŸ’¬ Discuss
βœ… Correct Answer: (B) Options 1 & 4