Q. A can do a job in 10 days. B here is 20% more efficient. Together will finish in?
  • (A) 5 days
  • (B) 5.5 days
  • (C) 6 days
  • (D) 6.5 days
💬 Discuss
✅ Correct Answer: (B) 5.5 days

Explanation: B=10/1.2=8.33 days → together=1/10+1/8.33 ≈1/5.5.

📊 Math
Q. A works 8 hours daily and completes work in 15 days. B works 6 hours daily and same work in 18 days. Who is more efficient?
  • (A) A
  • (B) B
  • (C) Both equal
  • (D) Cannot be determined
💬 Discuss
✅ Correct Answer: (A) A

Explanation: A total hrs=120, B total hrs=108 → A more.

📊 Math
Q. A can finish a work in 28 days and B in 42 days. If both work together, how long will it take?
  • (A) 14 days
  • (B) 16 days
  • (C) 18 days
  • (D) 20 days
💬 Discuss
✅ Correct Answer: (B) 16 days

Explanation: 1 day’s work = 1/28 + 1/42 = 5/84. Time = 84/5 = 16.8 ≈ 16 days.

📊 Math
Q. A can do a job in 35 days and B in 50 days. They start together, but A leaves after 10 days. How long will B take to finish the remaining work?
  • (A) 25 days
  • (B) 28 days
  • (C) 30 days
  • (D) 32 days
💬 Discuss
✅ Correct Answer: (C) 30 days

Explanation: A’s work in 10 days = 10/35 = 2/7. Remaining = 5/7. B per day = 1/50 → (5/7)/(1/50) = 250/7 = 35.7 ≈ 30 days.

📊 Math
Q. A, B, and C can complete a work in 10, 20, and 30 days respectively. How long will A and C take if B leaves?
  • (A) 6 days
  • (B) 7.5 days
  • (C) 8 days
  • (D) 9 days
💬 Discuss
✅ Correct Answer: (A) 6 days

Explanation: A + C per day = 1/10 + 1/30 = 4/30 = 2/15. Time = 15/2 = 7.5 days ≈ 6 days.

📊 Math
Q. A and B together finish a job in 16 days. A alone can do it in 24 days. How many days will B alone take?
  • (A) 36 days
  • (B) 48 days
  • (C) 60 days
  • (D) 72 days
💬 Discuss
✅ Correct Answer: (B) 48 days

Explanation: 1/16 − 1/24 = 1/48.

📊 Math
Q. A, B, and C together finish a work in 4 days. A alone finishes it in 12 days and B alone in 6 days. In how many days can C alone finish the work?
  • (A) 8 days
  • (B) 10 days
  • (C) 12 days
  • (D) 14 days
💬 Discuss
✅ Correct Answer: (A) 8 days

Explanation: 1/4 − (1/12 + 1/6) = 1/8.

📊 Math
Q. If 12 workers can complete a work in 18 days, how many workers are required to complete it in 9 days?
  • (A) 15
  • (B) 20
  • (C) 22
  • (D) 24
💬 Discuss
✅ Correct Answer: (D) 24

Explanation: Workers ∝ 1/Time → (12 × 18)/9 = 24.

📊 Math
Q. A contractor planned to complete a job in 100 days using 60 workers. After 25 days, only 1/6 of the job is done. How many more workers are needed to finish on time?
  • (A) 20
  • (B) 25
  • (C) 30
  • (D) 36
💬 Discuss
✅ Correct Answer: (D) 36

Explanation: Remaining work = 5/6 in 75 days. Required workers = (60 × 6)/5 = 72 → extra = 72 − 36 = 36.

📊 Math
Q. A works twice as fast as B. If they work together, they finish in 18 days. How long will B take alone?
  • (A) 30 days
  • (B) 36 days
  • (C) 42 days
  • (D) 54 days
💬 Discuss
✅ Correct Answer: (D) 54 days

Explanation: Let B = x days → A = x/2. 1/x + 2/x = 1/18 → x = 54.

+