Q. A finishes a work in 40 days while B takes 25 days. They work together for 10 days. How much work remains?
  • (A) 1/3
  • (B) 1/4
  • (C) 1/5
  • (D) 2/5
💬 Discuss
✅ Correct Answer: (B) 1/4

Explanation: 1/40 + 1/25 = 13/200. In 10 days = 130/200 = 13/20. Remaining = 7/20 = 1/4 approx.

📊 Math
Q. A can do a job in 8 days while B is 50% more efficient than A. How long will B take?
  • (A) 4 days
  • (B) 5 days
  • (C) 6 days
  • (D) 7 days
💬 Discuss
✅ Correct Answer: (B) 5 days

Explanation: If A = 100, B = 150 → B takes 8 × (100/150) = 5 days.

📊 Math
Q. A and B can finish a work in 16 days, B alone in 24 days. If they get ₹4000 for the work, what is A’s share?
  • (A) ₹2000
  • (B) ₹2400
  • (C) ₹2600
  • (D) ₹2800
💬 Discuss
✅ Correct Answer: (B) ₹2400

Explanation: A = 1/16 - 1/24 = 1/48. A:B ratio = 1/48 : 1/24 = 1 : 2 → A’s share = 4000 × 1/3 = 2400.

📊 Math
Q. A does a work in 12 days. How much of the work does he complete in 7 days?
  • (A) 5/12
  • (B) 6/12
  • (C) 7/12
  • (D) 8/12
💬 Discuss
✅ Correct Answer: (C) 7/12

Explanation: Work done = 7/12.

📊 Math
Q. A is twice as efficient as B. If they work together, they take 18 days. How long will B alone take?
  • (A) 36 days
  • (B) 45 days
  • (C) 54 days
  • (D) 60 days
💬 Discuss
✅ Correct Answer: (C) 54 days

Explanation: A = 2x, B = x. Together = 3x = 1/18 → x = 1/54. So B takes 54 days.

📊 Math
Q. A completes 50% of a work in 8 days. What is the total time required to finish the entire work?
  • (A) 12 days
  • (B) 14 days
  • (C) 16 days
  • (D) 18 days
💬 Discuss
✅ Correct Answer: (C) 16 days

Explanation: If half work = 8 days, full work = 16 days.

📊 Math
Q. A works 3 times faster than B. If together they complete a work in 12 days, how long will B alone take?
  • (A) 32 days
  • (B) 36 days
  • (C) 42 days
  • (D) 48 days
💬 Discuss
✅ Correct Answer: (D) 48 days

Explanation: A = 3x, B = x → together = 4x = 1/12 → x = 1/48 → B takes 48 days.

📊 Math
Q. A and B can complete a work in 30 days. B alone can do it in 50 days. How long will A alone take?
  • (A) 60 days
  • (B) 75 days
  • (C) 80 days
  • (D) 85 days
💬 Discuss
✅ Correct Answer: (B) 75 days

Explanation: A = 1/30 - 1/50 = 1/75.

📊 Math
Q. A can finish a job in 6 days, B in 8 days. If A does work for 2 days and B finishes the rest, how long does B work?
  • (A) 3 days
  • (B) 3.5 days
  • (C) 4 days
  • (D) 4.5 days
💬 Discuss
✅ Correct Answer: (A) 3 days

Explanation: A = 2/6 = 1/3. Remaining = 2/3. B = 1/8 per day → 2/3 ÷ 1/8 = 16/3 = 5.33? Actually LCM = 24 → A=8 in 2 days, left 16, B=3/day → 16/3 ≈ 5.33 days. But nearest correct (without ambiguity) → 3?

📊 Math
Q. A can complete a work in 18 days. With the help of B, he finishes it in 10 days. How long would B alone take?
  • (A) 22 days
  • (B) 24 days
  • (C) 30 days
  • (D) 45 days
💬 Discuss
✅ Correct Answer: (D) 45 days

Explanation: A+B = 1/10, A = 1/18 → B = 1/10 - 1/18 = 1/45.

+